The chimney gets a little taller

 

At the end of today, February 16, the chimney has grown a little taller.  The flue pipe was completed late this afternoon.  So tomorrow will bring an installation of a 13 foot flue into the chimney base.  The overall height of the chimney will be 17 feet.

 

This view shows the corner of the master bedroom in the foreground.  The chimney in the background is pretty much at the 8 foot mark.  Both columns which will support the patio roof are visible.

 

 

This view is straight on to the patio.  Notice the decorative work at the base of the columns.

 

This view shows the carport. The foreground corner is the utility room.  The corner where the windows are is the kitchen area.  In the background is Dino's house. 

 

This view shows where the driveway will approach looking north.  The front of the house is to the right.  The foreground column supports the carport roof.  The two in the background support the drive up roof which will allow entry to the house while providing protection from the elements.

 

 

The wall in the foreground is the support for the island that will provide additional workspace and seating in the kitchen area in the great room.

 