More concrete work

 

More concrete work today.  More of the sidewalk gets poured and the hearth floor in the fireplace also got poured.

 

 

This view shows the sidewalk being formed around the back of the pump house.  Raw dumped concrete is seen to the left side of the pump house.

 

 

The hearth floor is formed.  The opening for the fireplace is just about completed.  Some rebar needs to be cut and finish work around the edges is pending.  Fire cement will cover the inside and then brick pavers will be set.

 

 

Fifi shovels sand into the mixer.  Dino's house is in the background.

 

 

The shower wall as viewed from inside the master bathroom.  The vertical lines in the walls will hold glass block walls for the shower.

 

Juan floats the freshly laid concrete sidewalk around the pump house.

 